North Central Ohio
Advanced powered-land campus
An advanced, gigawatt-scale campus with land control, a drafted master plan, completed diligence, and both on-site and grid power work underway.
- Campus capacity
- 1+ GW
- Developable campus
- ~700 ac
- First power target
- Q4 2028
- Available water
- 2–2.5 MGD
- Capacity
- 1+ GW campus capacity
- Power status
- 900 MW on-site generation plus 100 MW FirstEnergy; DLS underway
- Gas
- Twin 42-inch Rover pipelines within 0.5 mile
- Acreage
- 607 acres optioned; approximately 700-acre developable campus
- Fiber
- Windstream and Zayo within approximately 2 miles; two-carrier, two-route model
- Water
- 2–2.5 MGD available; delivery requires new mains and reinforcement
- Transmission
- 100 MW FirstEnergy interconnection; DLS application submitted
- Zoning
- Portions zoned I-2 Industrial
- Target energization
- First on-site power targeted Q4 2028; 1 GW targeted Q4 2029
- Diligence complete
- Phase I ESA, water delineation, habitat/T&E, topographic survey, and preliminary load study; master site plan drafted